When loads get too big for forklifts and too precise for rough handling, teams turn to overhead cranes. This long-form walkthrough shows how a full overhead crane system comes to life inside a structural building. You’ll see preparation and surveys—with the same checklists pro installers use.
What an Overhead/Bridge Crane Is
An overhead crane rides on parallel runways anchored to a building frame, with a trolley that travels left-right along the bridge and a hoist that lifts the load. The system delivers three axes of motion: long-travel along the runway.
They’re the backbone of heavy shops and assembly lines, from beam handling to turbine assembly.
Why they matter:
Controlled moves for large, expensive equipment.
Less manual handling, fewer delays.
Lower risk during rigging, lifting, and transport inside facilities.
High throughput with fewer ground obstructions.
System Components We’re Installing
Runways & rails: continuous beams and rail caps.
End trucks: wheel assemblies that ride the rail.
Bridge girder(s): single- or double-girder configuration.
Trolley & hoist: reeving, hook block, upper limit switches.
Electrics & controls: power supply, festoon or conductor bars.
Stops, bumpers & safety: overload protection, e-stops.
Depending on capacity and span, the crane might be a single-girder 10-ton unit or a massive double-girder 100-ton system. The choreography is similar, but the scale, lift plans, and checks grow with the tonnage.
Before the First Bolt
Good installs start on paper. Key steps:
Drawings & submittals: Freeze the GA and verify reactions with the structural team.
Permits/JSAs: Job Safety Analysis (JSA) for each lift step.
Runway verification: Survey columns and runway beams for straightness, elevation, and span.
Power readiness: Lockout/tagout plan for energization.
Staging & laydown: Lay out slings, shackles, spreader bars, and chokers per rigging plan.
People & roles: Appoint a lift director, rigger, signaler, and electrical lead.
Tiny survey errors balloon into hours of rework. Spend time here.
Rails & Runways
Runway alignment is the foundation. Targets and checks:
Straightness & elevation: Laser or total station to set rail height.
Gauge (span) & squareness: Use feeler gauges on splice bars, torque rail clips.
End stops & buffers: Verify clearances for bumpers at both ends.
Conductor system: Mount conductor bars or festoon track parallel to the rail.
Log final numbers on the ITP sheet. Misalignment shows up as crab angle and hot gearboxes—don’t accept it.
Girder Erection & End Trucks
Rigging plan: Choose spreader bars to keep slings clear of electricals. Dedicated signaler on radio.
Sequence:
Lift end trucks to runway level and set temporarily on blocks.
For double-girder cranes, lift both girders with a matched raise.
Land the bridge on the end trucks and pin/bolt per GA.
Measure diagonal distances to confirm squareness.
Before anyone celebrates, bump-test long-travel motors gc construction with temporary power (under permit): confirm limit switch wiring. Lock out after test.
The Heart of the Lift
Trolley installation: Hoist/trolley arrives pre-assembled or as modules.
Hoist reeving: Lubricate wire rope; verify dead-end terminations.
Limits & load devices: Set upper/lower limit switches.
Cross-travel adjustment: Verify end stops and bumpers.
Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.
A smooth trolley with a quiet hoist is a sign of good alignment. Don’t mask issues with higher VFD ramps.
Electrics & Controls
Power supply: Drop leads tagged and strain-relieved.
Drive setup: Program VFDs for soft starts, decel ramps, and brake timing.
Interlocks & safety: E-stops, limit switches, anti-collision (if multiple cranes), horn, beacon.
Cable management: Secure junction boxes; label everything for maintenance.
Commissioning crews love clean labeling and clear folders. Photos of terminations help later troubleshooting.
ITP, Checklists, and Sign-Off
Inspection Test Plan (ITP): Third-party witness for critical steps.
Torque logs: Record wrench serials and values.
Level & gauge reports: Note any corrective shims.
Motor rotation & phasing: Document bump tests.
Functional tests: Jog commands, inching speeds, limits, overloads, pendant/remote range.
A tidy databook speeds client acceptance.
Ready for Work
Static load test: Apply test weights at the hook (usually 100–125% of rated capacity per spec).
Dynamic load test: Travel long-run, cross-travel, and hoist at rated speed with test load.
Operational checks: Limit switches trigger reliably; overload trips; horn/beacon function.
Training & handover: Maintenance intervals for rope, brakes, and gearboxes.
Only after these pass do you hand over the keys.
Where These Cranes Shine
Construction & steel erection: placing beams, trusses, and precast.
Oil & gas & power: moving heavy pumps, skids, and pipe spools.
Steel mills & foundries: large part transfer.
Warehousing & logistics: bulk material moves with minimal floor traffic.
Once teams learn the motions, cycle times drop and safety improves.
Do It Safe or Don’t Do It
Rigging discipline: dedicated signaler and stop-work authority.
Lockout/Tagout: clear isolation points for electrical work.
Fall protection & edges: approved anchor points, guardrails on platforms, toe boards.
Runway integrity: no cracked welds, correct bolt grades, proper grout.
Duty class selection: match crane class to cycles and loads.
Safety isn’t a stage—it's the whole show.
Keep It Rolling
Crab angle/drift: re-check runway gauge and wheel alignment.
Hot gearboxes: misalignment or over-tight brakes.
Rope drum spooling: dress rope and reset lower limit.
Pendant lag or dropout: shield noisy VFD cables.
Wheel wear & rail pitting: lubrication and alignment issues.
Little noises are messages—listen early.
Quick Answers
Overhead vs. gantry? Choose per site constraints.
Single vs. double girder? Span and duty class usually decide.
How long does install take? Scope, bay readiness, and tonnage rule the schedule.
What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.
Who Gets the Most Value
Students and pros alike get a front-row seat to precision rigging, structural alignment, and commissioning. You’ll gain a checklist mindset that keeps cranes safe and productive.
Want ready-to-use checklists for runway surveys, torque logs, and load-test plans?
Grab the installer pack so your next crane goes in cleaner, faster, and right the first time. Save it to your site tablet for quick reference.
...
Read more arabic articles...
read more about this products